20×30 House Construction Cost Estimator — Bengaluru

Small plot, tight setbacks, every rupee visible. Configure floors and tier for a 20×30 site and get the complete derived budget — including the approvals and site works that per-sqft rates skip.

Essential

₹25 – 42 lakh

Standard

₹28 – 48 lakh

Premium

₹34 – 61 lakh

For a typical configuration — adjust every parameter below. Indicative, confirmed after site assessment.

  • Written scope & quotation before any commitment
  • One accountable coordinator, start to finish
  • Screened execution professionals
  • Stage-by-stage payments, reviewed before the next stage
  • We never sell your requirement to contractors

A 20×30 (600 sqft) site yields roughly 500 sqft per floor after setbacks, which makes design discipline — and budget discipline — matter more than on any other plot size. Fixed costs like borewell, sanction and utility connections do not shrink with the plot, so they weigh proportionally heavier here: the honest per-sqft number for a small build is always higher than the headline rates suggest.

This estimator derives the full picture for your configuration, tier by tier, with sources and dates on every rate.

Interactive estimate

Build your estimate

Change any parameter — everything recomputes instantly from researched unit rates. No sign-up, no phone number required to see the numbers.

Your project

Quality tier

Estimated project cost · Standard

₹28 – 48 lakh

Timeline: 8–11 months

High confidenceBased on researched market rates — validated against real quotations over time

Advisory estimate for budgeting, not a quotation. A written, itemised Sevantay Realty quotation follows a free site assessment — and that document, not this page, is what you commit to. Includes GST at 18% and a 5–8% contingency.

Where the money goes

TMT steel Fe500 (~4.0 kg/sqft)

Consumption thumb rule: 3.5–4.5 kg per sqft of BUA — the model uses 4.0.

4000 × kg₹2.2 – 2.7 lakh
Cement (~0.45 bags/sqft)

Consumption: ~0.45 bags per sqft BUA including plaster (JK Cement, Happho).

450 × bag₹1.5 – 2 lakh
M-sand (~1.6 cft/sqft)

~1.6 cft per sqft BUA including plaster and flooring mortar.

1600 × cft₹72,000 – ₹1,04,000
Coarse aggregate (~1.2 cft/sqft)

~1.2 cft per sqft BUA.

1200 × cft₹45,600 – ₹66,000
Concrete blocks (~3.2/sqft)

~3.2 blocks per sqft BUA (brick-equivalent 25–35 ÷ 9).

3200 × block₹1 – 1.5 lakh
Civil labour — mason, helper, all trades

Mason ₹800–1,200/day, helper ₹450–700; central Bengaluru +15–25%.

1000 × sqft (BUA)₹2.3 – 3 lakh
Shuttering, centering, curing & consumables

Derived to reconcile component totals with audited turnkey bands — flagged for early calibration from real BOQs.

1000 × sqft (BUA)₹95,000 – ₹1,40,000
Terrace waterproofing — full system500 × sqft (terrace)₹60,000 – ₹1,10,000
Compound wall & gate (~100 rft)

Gate included as an averaged allowance; automation extra.

100 × rft₹95,000 – ₹1,60,000
Sump & overhead tank1 lumpsum₹1 – 1.6 lakh
Works subtotal
₹22 – 36 lakh
Design & consultant fees
₹65,000 – ₹1,79,000
GST (18%)
₹4 – 6.8 lakh
Contingency (5–8%)
₹1.3 – 3.5 lakh
Estimated total
₹28 – 48 lakh
Effective all-in cost per sqft₹2,770 – ₹4,790Small plots always run higher per sqft than headline rates — this is why.
Steel & cement (derived quantities)3,500–4,500 kg TMT · 400–500 cement bagsThumb rules per sqft BUA (Happho 500-project average, JK Cement). Cross-check any contractor BOQ against these.
Sand, aggregate & paint (derived)1,500–1,800 cft sand · 1,000–1,350 cft aggregate · 140–180 L paintAdd 5–10% wastage. Steel trends to the top of the band for G+2+ and cantilevered designs.

Choose your tier with open eyes

Same project, three honest specifications. The differences are listed exactly — this is where budget decisions belong.

Essential

₹25 – 42 lakh

A sound, honest build with ISI-marked basics — the spec most "starting at" ads quietly describe.

  • M20 RCC, standard Fe500 steel, solid-block masonry
  • Vitrified tiles ~₹60–80/sqft, flush doors, UPVC basic windows
  • Tractor-class emulsion, Cera/Hindware-class sanitaryware
  • Right where a 20×30 budget is the binding constraint

Standard

selected

₹28 – 48 lakh

The spec most families actually build — branded materials, better waterproofing, cleaner detailing.

  • M20/M25 mix as design demands, branded cement (UltraTech/ACC class)
  • GVT tiles ~₹80–120/sqft, teak-finish main door, UPVC windows
  • Apcolite-class paints, Jaquar-class CP fittings
  • Proper terrace waterproofing system, not just a chemical coat

Premium

₹34 – 61 lakh

Designer elevation, large-format finishes, premium brands — the house photographs like a project.

  • Elevation features (cladding, pergolas, cantilevers) engineered in
  • Large-format/imported tiles, hardwood doors, premium UPVC/aluminium
  • Royale-class paints, Kohler/Grohe-class bathrooms
  • Automation-ready electrical, designer lighting

Where can I save?

Compare like-for-like quotations

3–8%

Three contractors quoting the "same" house differ by lakhs in steel brand, wall thickness and fixture allowances. Normalising quotes before choosing routinely saves more than any material downgrade.

Phase the build structurally

defers 25–40%

Design columns and footing for the full height but build fewer floors now. The extra structural cost is small; retrofitting strength later is impossible.

Tile and sanitaryware timing

1–3% of total

Finish materials bought during festival-season dealer schemes save 10–20% on tiles, CP fittings and paints without changing the specification.

Keep the footprint simple

2–6%

Every cantilever, curved wall and level change adds shuttering and labour. A clean rectangle with a considered elevation costs less than a complicated massing with a plain one.

Assumptions, unit rates and sources behind this estimate
Rate usedUnitStandard bandBasisAs of
TMT steel Fe500/550D (JSW/Tata class)per kg₹56 – ₹68Research · tatanexarc.com, buildmaadi.com2026-08
Cement 50kg bag (UltraTech/ACC/Birla class)per bag₹340 – ₹450Research · varnahomes.in, buildmaadi.com2026-08
M-sand (structural + plaster)per cft₹45 – ₹65Research · alphasand.in, varnahomes.in2026-08
Coarse aggregate (20mm/12mm)per cft₹38 – ₹55Research · infralens.in, houseyog.com2026-08
Solid concrete blocks (6"/4" mix)per block₹32 – ₹48Research · alphasand.in, indiamart.com2026-08
Civil labour — all trades (labour-contract basis)per sqft (BUA)₹230 – ₹300Research · architects4design.com, relgrow.com2026-08
Shuttering, centering, curing, scaffolding & consumablesper sqft (BUA)₹95 – ₹140Research · houseyog.com, jkcement.com2026-08
Terrace waterproofing — full system (screed + membrane)per sqft (terrace)₹120 – ₹220Research · asianpaints.com, houseyog.com2026-08
Flooring — tiles supplied + laidper sqft (floor)₹140 – ₹210Research · mytyles.com, morbitilehub.com2026-08
Main door — door, frame, hardware, installper door₹32,000 – ₹62,000Research · tfsworld.in2026-08
Internal doors — flush door, frame, hardwareper door₹9,000 – ₹16,000Research · tfsworld.in, nobroker.in2026-08
Windows — UPVC/aluminium, glazed & installedper sqft (window)₹500 – ₹750Research · mccoymart.com, nobroker.in2026-08
Interior painting (walls + ceiling)per sqft (paintable)₹28 – ₹40Research · aapkapainter.com2026-08
Exterior painting (Asian Paints ladder)per sqft (wall)₹28 – ₹42Research · aapkapainter.com2026-08
Electrical — wiring, points, DBs (Polycab/Havells wire class)per sqft (BUA)₹32 – ₹50Research · houseyog.com, civillane.com2026-08
Bathroom — plumbing, waterproofing, tiling, sanitaryware & CPper bathroom₹1 lakh – ₹1.7 lakhResearch · renubath.in, housegyan.com2026-08
Kitchen & utility civil — counter base, dado, sink pointlumpsum₹40,000 – ₹80,000Research · houseyog.com, nobroker.in2026-08
Compound wall (5–6 ft masonry) with MS gateper rft₹950 – ₹1,600Research · houseyog.com, aecord.com2026-08
RCC sump (~10,000 L) + overhead tanklumpsum₹1 lakh – ₹1.6 lakhResearch · ekaplumbingbangalore.com, architects4design.com2026-08
BBMP plan sanction, khata & scrutiny (up to G+2)lumpsum₹40,000 – ₹90,000Research · sturdygroups.com, aecord.com2026-08
BESCOM power + BWSSB water/sanitary connections & depositslumpsum₹35,000 – ₹90,000Research · citizenmatters.in, nobroker.in2026-08

Researched rates are refreshed as the market moves; calibrated rates are updated from anonymised, aggregated Sevantay Realty quotations and invoices. No individual vendor or customer pricing is ever identifiable.

Turn this estimate into a real, written quotation

A free site assessment converts these ranges into your number — itemised, with material brands named, and payable stage by stage. No advance until you approve the scope.

What moves this cost most

  • Floors — ~500 sqft per floor; staircases eat a real share at this size
  • Fixed site costs — sanction, sump and utilities weigh heavier on small plots
  • Finish tier and soil condition, exactly as on larger plots

Commonly excluded from quotes

  • Land cost, stamp duty and registration
  • Interiors: modular kitchen, wardrobes, loose furniture
  • Elevation extras beyond the chosen tier (stone cladding, landscape)
  • Rainwater harvesting beyond the statutory minimum
  • Solar water heater / solar power systems

Hidden costs to budget for

  • Rock excavation if hard strata is hit — ₹1–4 lakh on bad plots
  • Betterment charges in newly added BBMP wards
  • Water tankers during construction if the borewell disappoints
  • Labour cess and design changes mid-build — the classic budget eaters
  • Deep borewells: Bengaluru increasingly needs 800–1,200 ft

Common questions

What does a 20x30 G+2 house cost in Bengaluru?

All-in at Standard tier — approvals, sump, GST and contingency included — this model computes roughly ₹40–66 lakh for G+2. The oft-quoted ₹25 lakh figures describe bare Essential construction with everything else excluded.

Is per-sqft cost higher on a 20x30 than a 30x40?

Yes, usually by 4–8%. Fixed costs spread over less area, and small sites are slower to work: material handling, shuttering reuse and labour minimums all bite.

G+3 on a 20x30 — sensible?

Where FAR and road width permit, G+3 with rental floors is a common and rational build. The staircase consumes proportionally more area, so unit layouts need real design care.