How to Compare Contractor Quotations Like for Like

Three quotations for the same job are rarely for the same job. A practical method for interiors, fit-outs, civil and facade work: normalise scope, specifications, quantities, GST and exclusions before you compare totals.

The lowest total is the most misleading number on a quotation. Contractors price what they think you asked for, leave out what they think you will not notice, and name brands only when it helps them. Comparing quotations properly means making them describe the same work first — then the totals mean something.

Step 1 — Write the scope before you ask

A one-paragraph requirement produces quotations you cannot compare. A numbered scope with quantities — areas, counts, lengths — and the specification you expect produces quotations you can. If drawings exist, every contractor should price the same set.

Step 2 — Normalise line by line

  • Scope: is every item in your list priced in every quotation? Mark gaps as "not quoted", not zero.
  • Quantities: measured or assumed? Different quantities for the same room mean someone guessed.
  • Specifications and brands: plywood grade, laminate, hardware, paint system, gypsum board, glass, cable make. Unnamed brands are the cheapest brands.
  • Lump sums: ask for lump sums to be broken down; they hide quantity and rate differences.
  • GST: included or extra, and at what rate. Compare totals on the same basis.
  • Exclusions: electrical points, civil changes, HVAC, debris removal, society or building charges, permissions.

Step 3 — Read the terms, not just the price

  • Payment terms: a large advance shifts risk to you; stage payments tied to completed work do not.
  • Timeline: days to complete, and what happens if it slips.
  • Validity: material prices move — how long is this price good for?
  • Variation rates: the price of extra work, agreed before it is needed.
  • Warranty: what is covered, for how long, and what voids it.
  • Supervision: who is on site every day.

A worked example

Three quotations for gypsum false ceiling and painting in a 3,000 sq ft office (illustrative):

Quote AQuote BQuote C
Total quoted₹3.9 lakh₹4.6 lakh₹4.2 lakh
GSTExtraIncludedExtra
Ceiling boardNot namedBranded 12.5 mmBranded 12.5 mm
Paint system1 coat putty, 2 coats2 coats putty, 2 coats emulsion2 coats putty, 2 coats emulsion
Cove lighting cut-outsNot quotedIncludedIncluded
Debris removalExcludedIncludedIncluded
Like-for-like total incl. GST≈ ₹5.1 lakh after adding gaps₹4.6 lakh≈ ₹5.0 lakh
Illustrative example. After adding GST and pricing the gaps, the "cheapest" quotation is the most expensive.

Or let us do the comparison

Sevantay Realty runs this process for customers: we write the brief, collect quotations from matched contractors in our network, normalise them, and show them to you side by side as Option A, B and C — contractor identities protected until you choose who to meet.

Common questions

How many quotations should I get?

Three is the useful number: enough to see the market rate and an outlier, few enough that you can compare them properly.

Should I always pick the lowest quotation?

Only after the quotations describe the same work. Once gaps are priced and GST is on the same basis, the lowest like-for-like total is a fair choice — subject to timeline, payment terms and the contractor’s track record.

What is a comparative statement?

A table that lists each quotation’s rates and amounts against the same scope items, with exclusions and terms — the format companies use to approve a vendor.